Consider the following table which describes the activities to be done to Build A House and it's sequence.


(Click to enlarge)

Task
1) Construct the network Diagram
2) Find the critical path

Answer:

1) The network diagram

(Click to enlarge)

2) The critical path


(Click to enlarge)

The critical path is A+B+D+G since it takes the longest duration to finish the project.